Permit Timelines — 2026

How Long Does a Florida Permit Really Take?

“When can I start building?” is the first question every homeowner asks. The honest answer: it depends on your county, the completeness of your package, and whether the plans examiner has questions. Here are realistic 2026 timelines — and how to land on the fast end of them.

By Cleber Franca, PE (FL #102290) · Published August 16, 2026 · 7 min read

The short version

Most residential accessory permits clear plan review in 5–20 business days once a complete package is submitted. The engineering drawings take about 5–7 business days to prepare. The single biggest variable is not the county — it is whether your submission is complete and code-compliant on the first pass.

The three stages of a Florida permit

“How long does a permit take” blends three separate clocks. Understanding them tells you where the time actually goes:

  1. Engineering (5–7 business days): preparing the PE-stamped structural drawings, wind-load calculations, and connection details your county requires.
  2. Plan review (5–20 business days): the county's clock. The plans examiner checks your package against the Florida Building Code and either approves it or issues comments.
  3. Inspections (during construction): footing, framing, and final inspections scheduled as the work progresses — usually 1–2 days' notice each.

Plan-review times by Florida county (2026)

These are typical first-review windows for straightforward residential accessory projects. They fluctuate with the county's workload — review times often lengthen right after major storms, when re-roof and repair permits flood the queue.

CountyTypical first reviewNotes
Orange (Orlando)~10–15 business daysOnline submittal via Fast Track
Osceola (Kissimmee)~7–12 business daysSmaller queue than Orange
Polk~7–14 business daysFaster in outlying areas
Lake~7–12 business days
Hillsborough (Tampa)~10–20 business daysHigh volume
Lee (Fort Myers)~10–20 business daysLonger post-storm
Miami-Dade / Broward~15–30 business daysHVHZ & NOA review adds time
These are first-review times, not total times. If the plans examiner issues comments, responding to them starts a second review cycle — often another 5–15 business days. Clearing review on the first pass is the whole game.

What decides whether you wait 1 week or 6

1. Completeness of the package

The number-one cause of delay is a package that is missing something: unsigned drawings, no wind-load calculations, a missing product approval, or no site plan. Every missing item triggers a rejection and a fresh review cycle. A complete PE-sealed package is the difference between one review and three.

2. County and jurisdiction

Inland counties like Osceola, Polk, and Lake generally move faster than high-volume metros. Miami-Dade and Broward take longest because HVHZ rules require Notice of Acceptance (NOA) product review on top of the standard code check.

3. Timing and season

After a named storm, counties are buried in re-roof and repair permits, and review times stretch. Submitting before hurricane season — or early in the week — can shave days off your wait.

The hidden delay: after-the-fact permits

If you already built without a permit, expect the timeline to roughly double. The county treats it as an after-the-fact permit, often charging double fees and requiring the engineer to evaluate the existing structure before drawings can even be submitted.

How to land on the fast end

Want the fast lane through plan review?

We prepare complete, county-specific packages that are built to clear review on the first pass — quoted same day, drawings usually ready in 5–7 business days.

Start Your Project →

Frequently asked questions

How long does a residential building permit take in Florida?

For a typical accessory structure — pergola, screen enclosure, slab, patio — plan review runs about 5 to 20 business days depending on the county, plus one more cycle if comments are issued. Most straightforward projects are approved within 2 to 5 weeks of a complete submission.

What is the fastest way to get a Florida permit approved?

Submit a complete, code-compliant package the first time: PE-stamped drawings, wind-load calculations for your county, product approvals, and a site plan. Incomplete submissions and unsigned drawings are the leading cause of extra review cycles.

Can I start building while the permit is under review?

No. Starting work before the permit is issued is building without a permit, which exposes you to stop-work orders, fines, and after-the-fact penalties. Wait for the approved permit card before breaking ground.